KEY DATES

Major Project Milestones

MILESTONE DATE
PWPA Effective Date 18th January 2005
Closing Date 25th April 2005
Payment Date / Financial Close 6th July 2005
LNTP Refurbishment Works 18th April 2005
LNTP New B Extension 15th July 2005
FNTP Refurbishment Works 6th July 2005
FNTP New B Extension 30th September 2005
Group 1 COD (+450MW + 30MIGD) 28th May 2008
Project COD (2000MW 160 MIGD) 30th October 2008
Outage Season Starting  1st of NovemberEvery Year
Outage Season Ending  31st of March Every Year
PWPA Ending 18th January 2028